Petition No. 158/MP/2012. Case: DPSC Limited, Kolkata Vs Power Grid Corporation of India Limited, New Delhi and West Bengal State Electricity Transmission Company Limited, Kolkata. Central Electricity Regulatory Commission

Case NumberPetition No. 158/MP/2012
JudgesDr. Pramod Deo, Chairperson, Shri S. Jayaraman, Member and Shri M. Deena Dayalan, Member
IssueElectricity Act, 2003 - Sections 38 (2), 42, 43, 79(1)(c), 79 (1)(f)
Judgement DateSeptember 21, 2012
CourtCentral Electricity Regulatory Commission

Order:

(New Delhi)

  1. The petitioner, DPSC Limited (DPSCL) has filed the present petition under

    the Regulation 32 of the Central Electricity Regulatory Commission (Grant of

    Connectivity, Long Term Access and Medium-Term Open Access in Inter-State

    Transmission and Related Matters), Regulations 2009 (the Connectivity

    Regulations) seeking directions to Power grid Corporation of India Limited to

    grant connectivity to the petitioner in terms of its application dated

    10.5.2011 in a time bound manner. The Petitioner is a company engaged in

    distribution of electricity over an area of approximately 618 kms in

    Asansol-Raniganj belt of West Bengal. The

    Petitioner has submitted that its current distribution network is an isolated

    grid in a radial mode which is neither connected to the Central Transmission

    Utility nor to the State Transmission Utility. The Petitioner draws power

    through two 33/11 kV sub-stations from Damodar Valley Corporation and three

    33/11 kV sub-stations from West Bengal State Electricity Distribution Company

    Limited.

  2. The petitioner has submitted that with a view to address the increasing

    demand of electricity in its licensed area and to meet its obligation under

    Sections 42

    and 43

    of the Electricity Act, 2003, the Petitioner is required to arrange for

    procurement of power from various sources. In this context, it has become

    imperative that the Petitioner is connected with the grid. The Petitioner

    applied on 10.5.2011 to PGCIL for connectivity to the inter-State transmission

    system. The Petitioner has submitted that it has sought connectivity for 1000

    MW from PGCIL with the expected date of connectivity as July 2014. In the

    meeting between PGCIL and Phase 2 applicants for connectivity and long term

    access of Jharkhand, Bihar and West Bengal

    held on 29.7.2011, the petitioner requested for modification of connectivity

    requirement from 1000 MW to 500 MW. It was decided in the said meeting that

    since the responsibility for planning of power supply to DPSCL is within the

    purview WBSETCL, the matter needs to be addressed out on the advice of WBSETCL.

    Pursuant to the above decision, PGCIL issued a communication to WBSETCL

    requesting for its views and observations with regard to the Petitioner's

    application for grant of connectivity. The Petitioner communicated to WBSETCL

    requesting it to convey its comment with regard to the petitioner's application

    for connectivity. However, WBSETCL conveyed that it was not in a position to

    give its views in the absence of any proposed connection arrangement from CTU.

    The Petitioner in its letter dated 23.9.2011 submitted the following proposal

    to CTU with a request to elicit the views of WBSETCL thereon:

    For your information we want to set up a 400 kV sub-station

    at Chalbalpur in the district of Burdwan, West Bengal which is 14 kms away from

    your Maithon 400 kV S/s (Rupnarayanpur). We want to get connectivity at

    Chalbalpur by LILO of one circuit of Mejia-Maithon 400 kV double circuit line

    as suggested by you or Maithon-Purulia 400 kV double circuit line whichever

    would be suitable for PGCIL. Please note that the substation as well as the

    associated line would be constructed at our own cost.

    In the meeting of Standing Committee on Power System Planning in Eastern

    Region held on 8.2.2012, it was decided that the Petitioner should first take

    the regulatory approval from WBERC and then submit the proposal to WBSETCL for

    technical examination. The Petitioner in its letter dated 9.2.2012 sought the

    technical clearance of CEA for formulation of the transmission plan before

    submitting the application for investment approval. The Petitioner in its

    letter dated 27.6.2012 submitted before WBERC that it is not in a position to

    file any investment approval without clearance by WBSETCL and requested WBERC

    to direct WBSETCL to grant technical clearance to the petitioner for the

    proposed connectivity at the earliest. The Petitioner is stated to have written

    a letter to this Commission on 28.6.2012 to direct PGCIL to grant connectivity

    to the petitioner.

  3. It is against the above factual matrix...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT