WP(C) 225/2011. Gauhati High Court
Case Number | WP(C) 225/2011 |
Judgement Date | May 16, 2019 |
Court | Gauhati High Court |
I N THE GAUHATI HI GH COURT
(High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh)
WP( C) No.225 of 2011
Bhai Bandu Group ,
Represented by the President Habibul Shikh Having its registered office at Dhing Hinga, Under Gossaigaon Police Station,
District- Kokrajhar, (BTAD) Assam.
............ Petitioner
- Versus –
-
The Assam State Electricity Board,
Represented by the Chairman of the Board, Bijuli Bhawan Panbazar, Guwahati- 781001.
-
The Chairman,
Assam State Electricity Board,
Bijuli Bhawan Panbazar, Guwahati- 781001.
-
The Deputy General Manager,
Kokrajhar Electrical Division,
Lower Assam Electricity Distribution Company Limited (LEADCL), Kokrajhar
(BTAD), Assam.
-
The Senior Manager,
Kokrajhar Electrical Division,
Lower Assam Electricity Distribution Company Limited (LEADCL), Kokrajhar
(BTAD), Assam.
-
The Deputy Manager,
Gosaigaon Electrical Sub-Division, Lower Assam Electricity Distribution Company Limited (LEADCL), Gossaigaon, Kokrajhar (BTAD), Assam
-
The Sub-Divisional Engineer,
Gossaigaon Electrical Sub-Division,
Lower Assam Electricity Distribution Company Limited (LEADCL),Gossaigaon, Kokrajhar (BTAD), Assam
-
The Executive Engineer,
Kokrajhar Electrical Division,
Lower Assam Electricity Distribution Company
Limited (LEADCL), Kokrajhar
(BTAD), Assam.
-
Bodo Land Territorial Autonomous District Council,
Represented by the Principal Secretary, BTAD Kokrajhar, Assam.
........ Respondents
B E F O R E
HON’BLE MR. JUSTI CE A.M. BUJOR BARUA
For the petitioner: None appeared.
For the respondents: Mr.N.J. Dutta, SC APDCL.
Ms. B. Bhuyan, SC, BTC
Date of Hearing : 16.05.2017.
Date of Judgment: 16.05.2017.
JUDGMENT & ORDER ( ORAL)
None appears for the petitioner when the matter is called upon for hearing. Heard Mr. N.J. Dutta, learned Standing Counsel for the respondent APDCL and Ms. B. Bhuyan, learned Standing Counsel for the respondent BTC authorities.
-
The writ petitioner herein, being a NGO had entered into an agreement dated 01.03.2006 with the Assam State Electricity Board (ASEB), by which, it was provided that the ASEB desires to get the job of revenue realization from the persons using electricity from its source in some of the areas to be defined through a decided agency and the petitioner is agreeable and prepared to carry out the said job of realization of the monthly revenue along with some other works.
-
Clause-11 of the said agreement provides that the agency shall pay to the Board each month for the electrical energy...
To continue reading